top of page

Past Projects

Proven Performance Across All Job Sites

Browse projects by category to learn more about the scope, capabilities, and expertise behind the work we do every day.

 

Beaird Drilling has completed foundation drilling projects throughout Texas for commercial developments, infrastructure improvements, industrial facilities, transportation projects, and specialized low clearance applications. Our portfolio reflects decades of experience, trusted partnerships, and a commitment to delivering reliable results in demanding conditions.

Use > to Navigate
Amazon Fulfillment Center Pflugerville

Drilled pier and deep foundation work for Amazon Fulfillment Center Pflugerville, including drilled 1000 piers, 96' diameter 75' deep, delivered with schedule-focused field execution.

Commercial Drilling

The Conlan Company
Austin ISD Performing Arts Center - Austin TX

Drilled pier and deep foundation work for Austin ISD Performing Arts Center - Austin TX, including over 225 piers drilled and cased ranging from 18" to 42" in diameter, delivered with schedule-focused field execution.

Commercial Drilling

American Constructors
Oracle Corporate Campus Austin

Drilled drilled pier and deep foundation work for Oracle Corporate Campus Austin, including drilled and vibro-cased over 1,000 piers for high profile project. Completed the project safely and ahead of time, delivered with schedule-focused field execution.

Commercial Drilling

Ryan Companies US, INC
Riata Vista (Apple Campus)- Austin TX

Drilled drilled pier and deep foundation work for Riata Vista (Apple Campus)- Austin TX, including 300 piers 20+ feet of penetrations ranging from 18" to 48" piers, delivered with schedule-focused field execution.

Commercial Drilling

Cadence McShane
Hotel Van Zandt

Commercial drilled pier and deep foundation work for Hotel Van Zandt, including 230 Piers completed from 24" to 60" shafts. The entire length of shafts consisted of rock penetration (30+ feet), drilled 80' below street level, delivered with schedule-focused field execution.

Commercial Drilling

Tribble & Stevens
Hutto 9th Grade Center

Commercial drilled pier and deep foundation work for Hutto 9th Grade Center, including drilled and cased over 500 piers, 70' deep, delivered with schedule-focused field execution.

Commercial Drilling

Baird Williams Construction, Ltd
San Antonio State Hospital

Commercial drilled pier and deep foundation work for San Antonio State Hospital, including drilled and belled 400 piers 50' deep, delivered with schedule-focused field execution.

Commercial Drilling

Vaughn Construction
Galm Road High School

Drilled pier and deep foundation work for Galm Road High School, including drilled and cased over 800 piers 70' deep, delivered with schedule-focused field execution.

Commercial Drilling

Joeris General Contractors, Ltd
Kallison Ranch Middle School

Commercial drilled pier and deep foundation work for Kallison Ranch Middle School, including drilled and cased over 500 piers 65' in depth, delivered with schedule-focused field execution.

Commercial Drilling

Bartlett Cocke General Contractors
Pflugerville Hidden Lakes Elementary

Drilled pier and deep foundation work for Pflugerville Hidden Lakes Elementary, including drilled and cased over 1,500 piers, delivered with schedule-focused field execution.

Commercial Drilling

Webber, LLC
TAMU Science Tech

Commercial drilled pier and deep foundation work for TAMU Science Tech, including drilled and cased over 500 piers, delivered with schedule-focused field execution.

Commercial Drilling

SpawGlass
Texas A&M Univerisity - San Antonio TX

Commercial drilled pier and deep foundation work for Texas A&M Univerisity - San Antonio TX, including 300+ piers 3 different buildings averaging 65', delivered with schedule-focused field execution.

Commercial Drilling

Bartlett Cocke
Pflugerville Bohls Middle School

Drilled pier and deep foundation work for Pflugerville Bohls Middle School, including drilled and cased over 1,500 piers, delivered with schedule-focused field execution.

Commercial Drilling

Webber, LLC
ACC Highland Campus

Drilled pier and deep foundation work for ACC Highland Campus, including drilled under 15' of overhead clearance. Drilled 42' piers up to 30' deep, delivered with schedule-focused field execution.

Commercial Drilling

Flintco, LLC
Domain Building C1 and C6 - Austin TX

Commercial drilled pier and deep foundation work for Domain Building C1 and C6 - Austin TX, including over 175 piers completed exceeding schedule demands by 1 month, delivered with schedule-focused field execution.

Commercial Drilling

Austin Commercial
CFS Project: Flood Gate Apartments

Commercial drilled pier and deep foundation work for CFS Project: Flood Gate Apartments, including drilled, belled, and cased 300 piers up to 70� deep in downtown San Antonio, delivered with schedule-focused field execution.

Commercial Drilling

Jordan Foster Construction, LLC
Austin Park

Commercial drilled pier and deep foundation work for Austin Park, including 275 plus piers drilled 40+ feet and belled. Finished the project one month ahead of schedule, delivered with schedule-focused field execution.

Commercial Drilling

White Construction
Titan North

Commercial drilled pier and deep foundation work for Titan North, including drilled over 400 piers in rock, delivered with schedule-focused field execution.

Commercial Drilling

MW Builders
UT East Campus Parking Garage

Commercial drilled pier and deep foundation work for UT East Campus Parking Garage, including drilled and cased piers into rock, delivered with schedule-focused field execution.

Commercial Drilling

SpawGlass - Austin
University of Texas - Rowling Hall - Austin Tx

Commercial drilled pier and deep foundation work for Univerity of Texas - Rowling Hall - Austin Tx, including 200 piers 24" - 72" averaging 20' to 50' penetrations into rock, drilled 150' below street level, delivered with schedule-focused field execution.

Commercial Drilling

DPR
City of Austin Marshalling Yard

Drilled pier and deep foundation work for City of Austin Marshalling Yard, including drilled and vibro-cased over 300 piers 70' deep, delivered with schedule-focused field execution.

Commercial Drilling

SpawGlass - Austin
Austin State Hospital

Drilled pier and deep foundation work for Austin State Hospital, including drilled and cased 600 piers 50' deep, delivered with schedule-focused field execution.

Commercial Drilling

Turner Construction Company
South West ISD - San Antonio TX

Commercial drilled pier and deep foundation work for South West ISD - San Antonio TX, including over 900 piers comprised of 18" to 36" piers 40' deep, delivered with schedule-focused field execution.

Commercial Drilling

Joeris
Lackland Dorm ATC #6

Commercial drilled pier and deep foundation work for Lackland Dorm ATC #6, including drilled, belled, and cased piers; Up to 48' in diameter with 144 bell, 75' deep, delivered with schedule-focused field execution.

Commercial Drilling

SpawGlass San Antonio
University of Texas Liberal Arts Building - Austin TX

Commercial foundation drilling project for University of Texas Liberal Arts Building - Austin TX, supported by Beaird Drilling's experienced drilled pier and deep foundation team.

Commercial Drilling

SpawGlass
Red River Tower

Drilled drilled pier and deep foundation work for Red River Tower, including completed 42 and 72 drilled piers, and slurried/cased these piers on a large high-rise project in downtown Austin, delivered with schedule-focused field execution.

Commercial Drilling

Rogers O Brien Construction Company, LLC
Dell Children's Hospital

Commercial drilled pier and deep foundation work for Dell Children's Hospital, including 175 piers drilled all in hard rock, delivered with schedule-focused field execution.

Commercial Drilling

JE Dunn Construction Company
Urban East Multi-Family

Commercial drilled pier and deep foundation work for Urban East Multi-Family, including drilled and vibro-cased over 200 piers 70' deep, delivered with schedule-focused field execution.

Commercial Drilling

Bartlett Cocke General Contractors
SH 130 & Hwy 290 Interchange

Heavy civil drill shaft foundation work for SH 130 & Hwy 290 Interchange, including drilled and placed 96' diameter shafts up to 90' deep on new direct connectors, built for roadway, bridge, and infrastructure demands.

Heavy Civil

Webber, LLC
SH130 Segments 5 & 6

Heavy civil drill shaft foundation work for SH130 Segments 5 & 6, including 78 bridges from Austin (Hwy 183) to Seguin (I-10). Drill shaft sizes ranged from 18" to 96", built for roadway, bridge, and infrastructure demands.

Heavy Civil

Zachry Construction Corporation
FM 110 Hays County

Heavy civil drill shaft foundation work for FM 110 Hays County, including over 5,000 LF of turnkey drill shafts for new roadway, built for roadway, bridge, and infrastructure demands.

Heavy Civil

Hunter Industries
Bexar County Hausman Road

Heavy civil drill shaft foundation work for Bexar County Hausman Road, including over 3000 linear feet of drill shafts from 24" to 48" in diameter all of drilling has been penetrations into rock, built for roadway, bridge, and infrastructure demands.

Heavy Civil

Sundt
FM 685

Heavy civil drill shaft foundation work for FM 685, including over 1000 linear feet of 18" - 36" drill shafts, built for roadway, bridge, and infrastructure demands.

Heavy Civil

OHL
Coryell County SH 9

Heavy civil drill shaft foundation work for Coryell County SH 9, including 5 Bridges completed over a 3.5 Mile Loop. Over 4000 linear feet of drill shafts, built for roadway, bridge, and infrastructure demands.

Heavy Civil

Ledcor
FM 110

Heavy civil drill shaft foundation work for FM 110, including new highway construction. Finished ahead of schedule, built for roadway, bridge, and infrastructure demands.

Heavy Civil

James Construction Group, LLC
I-35 & Hwy 183 Interchange

Heavy civil drill shaft foundation work for I-35 & Hwy 183 Interchange, including turnkey drill shaft foundation for direct connect expansion, built for roadway, bridge, and infrastructure demands.

Heavy Civil

J.D. Abrams, L.P
Interstate-10

Heavy civil drill shaft foundation work for Interstate-10, including over 2700 linear feet of 24" to 36" drill shafts, built for roadway, bridge, and infrastructure demands.

Heavy Civil

Webber
My-35 Project

Heavy civil drill shaft foundation work for My-35 Project, including sections 1B, 1C, 2B, 3A1, and 3A2 over 50,000 linear feet of Drill Shafts on I-35 from Salado to West, Texas, built for roadway, bridge, and infrastructure demands over the course of five separate contracts.

Heavy Civil

James Construction
LBJ Tollway

Heavy civil drill shaft foundation work for LBJ Tollway, including noise Barrier Wall consisting of a 1 mile stretch over 800 drill shafts before encountering the low clearance drill shafts, built for roadway, bridge, and infrastructure demands.

Heavy Civil

Ferrovial
SH195

Heavy civil drill shaft foundation work for SH195, including over 1900 linear feet of 18" and 36" drill shafts, built for roadway, bridge, and infrastructure demands.

Heavy Civil

Sema
Wurzbach Parkway

Heavy civil drill shaft foundation work for Wurzbach Parkway, including consisting of 5 bridges and 1 noise barrier wall, built for roadway, bridge, and infrastructure demands.

Heavy Civil

Texas Sterling
Kenney Fort

Heavy civil drill shaft foundation work for Kenney Fort, including over 3500 linear feet of drill shafts ranging from 18" to 54" in diameter, built for roadway, bridge, and infrastructure demands.

Heavy Civil

Chasco
I-10

Heavy civil drill shaft foundation work for I-10, including turnkey drill shafts up to 60' deep for major expansion, built for roadway, bridge, and infrastructure demands.

Heavy Civil

Jordan Foster Construction, LLC
Highway 281

Heavy civil drill shaft foundation work for Highway 281, including drilled and placed drill shafts for major expansion on Highway 281, built for roadway, bridge, and infrastructure demands.

Heavy Civil

Zachry Construction Corporation
McLennan County Highway-35 Project

Heavy civil drill shaft foundation work for McLennan County Highway-35 Project, including section 5A and 14,500 linear feet of drill shafts. Sizes from 18" - 48" in diameter, built for roadway, bridge, and infrastructure demands.

Heavy Civil

Williams Brothers
Metro Center - Austin TX

Low clearance foundation drilling for Metro Center - Austion TX, including 200 Low Clearance Drill Shafts going 66' deep, using limited-access drilling methods for constrained jobsite conditions.

Low Clearance

Structure Tone
San Antonio Zoo

Low clearance foundation drilling for San Antonio Zoo, including hoisted limited access drilling rig to perform intricate cased pier project, using limited-access drilling methods for constrained jobsite conditions.

Low Clearance

Guido Construction Company
Union Pacific Railroad Tower 55 - Fort Worth TX

Low clearance foundation drilling for Union Pacific Railroad Tower 55 - Fort Worth TX, including 24" to 60" Low Clearance Drill Shafts, using limited-access drilling methods for constrained jobsite conditions.

Low Clearance

Jay Reese
Pearl Hotel - San Antonio Tx

Low clearance foundation drilling for Pearl Hotel - San Antonio Tx, including 40+ piers 40+ feet drilled, cased, and belled under 30' overhead clearance, using limited-access drilling methods for constrained jobsite conditions.

Low Clearance

Harvey Cleary
Omni - Barton Creek

Low clearance foundation drilling for Omni at Barton Creek, including drilled under 20' of overhead clearance on high profile expansion project, using limited-access drilling methods for constrained jobsite conditions.

Low Clearance

The Beck Group
Kalahari Resort

Low clearance foundation drilling for Kalahari Resort, including drilled and cased intricate limited access piers for water feature foundations, using limited-access drilling methods for constrained jobsite conditions.

Low Clearance

Patin Construction, LLC
Waterloo Tower - Austin

Low clearance foundation drilling for Waterloo Tower in Austin, including drilled under 15' and 200+ year oak trees, using limited-access drilling methods for constrained jobsite conditions.

Low Clearance

DPR Construction
Henry B. Gonzalez Convention Center - San Antonio TX

Drilled pier and deep foundation work for Henry B. Gonzalez Convention Center - San Antonio TX, including 400 plus piers 18" - 72" piers 144" bells ranging from 65' to 110', delivered with schedule-focused field execution.

Low Clearance

Hunt/Zachry Construction Corporation
Henry B. Gonzales Convention Center Garage - San Antonio TX

Low clearance foundation drilling for Henry B. Gonzales Convention Center Garage - San Antonio TX, including drilled under 20' overhead clearance. Piers were cased, drilled, and belled 65 deep, using limited-access drilling methods for constrained jobsite conditions.

Low Clearance

Not Applicable
Hyatt Ballroom - LaCantera - San Antonio TX

Low clearance foundation drilling for Hyatt Ballroom - LaCantera - San Antonio TX, including drilled with 9' overhead clearance. Piers were 20' deep penetrating into extremely hard rock, using limited-access drilling methods for constrained jobsite conditions.

Low Clearance

Harvey Cleary
Waller Creek Expansion

Low clearance foundation drilling for Waller Creek Expansion, including turnkey drill shaft construction of detailed expansion project, using limited-access drilling methods for constrained jobsite conditions.

Low Clearance

Zachry Construction Corporation
Valero Corporate Campus Expansion

Low clearance foundation drilling for Valero Corporate Campus Expansion, including drilled 200 piers into hard rock with 15' overhead clearance inside existing building, using limited-access drilling methods for constrained jobsite conditions.

Low Clearance

Structure Tone Southwest
Mopac Improvement Project

Low clearance foundation drilling for Mopac Improvement Project, including noise barrier wall 1600 low clearance drill shafts, using limited-access drilling methods for constrained jobsite conditions.

Low Clearance

CTRMA
LBJ Tollway

Low clearance foundation drilling for LBJ Tollway, including noise Barrier Wall 1200 low clearance drill shafts, using limited-access drilling methods for constrained jobsite conditions.

Low Clearance

Ferrovial
American Airlines Corporate Campus Ft. Worth

Drilled pier and deep foundation work for American Airlines Corporate Campus - Ft. Worth, including drilled, cased, placed, and poured over 1000 piers. Beat the schedule by over 1 month, delivered with schedule-focused field execution.

Turn Key Solutions

Austin Commercial
Baylor East Village - Waco TX

Commercial drilled pier and deep foundation work for Baylor East Village - Waco TX, including (Turnkey) Over 350 piers drilled and poured completed 1 month ahead of schedule, delivered with schedule-focused field execution.

Turn Key Solutions

Beck Group
Baylor Paul L. Foster Business School - Waco TX

Drilled pier and deep foundation work for Baylor Paul L. Foster Business School - Waco TX, including (Turnkey) Drilled and Poured 200 piers, finishing job 3 weeks ahead of schedule, delivered with schedule-focused field execution.

Turn Key Solutions

Flintco
University of Texas Southwestern Expansion Dallas

Drilled pier and deep foundation work for University of Texas Southwestern Expansion - Dallas, including 100% Turnkey Drilled Pier Package. Piers up to 72' in diameter and 150' deep. Finished the project ahead of schedule, delivered with schedule-focused field execution.

Turn Key Solutions

Austin Commercial
ABIA Terminal Expansion

Drilled pier and deep foundation work for ABIA Terminal Expansion, including turnkey drilled and vibro-cased over 500 piers 75' deep, delivered with schedule-focused field execution.

Turn Key Solutions

Hensel Phelps Construction Company
Skyhouse Apartment Homes - Austin TX

Drilled pier and deep foundation work for Skyhouse Apartment Homes - Austin TX, including (Turnkey) Drilled and poured 40 piers 54" to 96" processed to 50' cased and completed at 65', delivered with schedule-focused field execution.

Turn Key Solutions

Batson Cook
bottom of page